Scope of Works
The works will consist of carriageway resurfacing in asphalt and repaving of footpaths with new granite, rehabilitation of a section of water-main, installation of new traffic and public lighting infrastructure, and street furniture.
Access will be maintained to premises at all times as part of the agreed Traffic Management Plans.
We apologise in advance for any inconvenience that may be caused during these improvement works. Every effort will be made to ensure that disruption is kept to a minimum at all times.
Project Updates
During the course of the project, we will provide regular updates here regarding the works, including:
- Work completed
- Work to be undertaken in the coming weeks
- Any special information relating to the works
Meanwhile, if you have any questions or concerns, you can contact [email protected]
There is also a dedicated website set up for the Barrow Street Public Realm Scheme www.dublincity.ie/residential/transportation/roads-and-traffic-projects/barrow-street-public-realm-scheme
March 2025 – Week 1
Works at Phase 3A (From Mason Hayes – Ringsend Road)
- Paving
- Setting Out
- Grouting Paving
- Erect site fencing around area works
- Tree pit Excavation
- Tree pit plinth foundation
- Landscaping work
- Resin Bound
March 2025 – Week 2
Works at Phase 3B (From Tots & Co – Ringsend Road)
- Proposed Hippo Road Gully
- Manhole Ring Installation
- Proposed Catchpit Chamber E600 will be installed
- Proposed Catchpit manhole to be built
- Drain Line connection
- Setting Out
- Breaking Footpath
- Paving outside tots
- Kerb Laying
- Pipe Connection into manhole
- Set up temporary Traffic Management
- Erect site fencing around area works
- Phase 3B footpath work
- Road crossing sets
- Tree pits excavation
- Tree pits plinth foundation
- Build out kerbs laying