Actavo Ireland is delighted to have been appointed to carry out the Barrow Street Public Realm Improvement Scheme Project, from its Junction with Grand Canal Street Upper to its Junction with Ringsend Road. The current plan is that works will commence in January 2024.

Scope of Works

Scope of Works

The works will consist of carriageway resurfacing in asphalt and repaving of footpaths with new granite, rehabilitation of a section of water-main, installation of new traffic and public lighting infrastructure, and street furniture.

Access will be maintained to premises at all times as part of the agreed Traffic Management Plans.

We apologise in advance for any inconvenience that may be caused during these improvement works. Every effort will be made to ensure that disruption is kept to a minimum at all times.

Project Updates

During the course of the project, we will provide regular updates here regarding the works, including:

  • Work completed
  • Work to be undertaken in the coming weeks
  • Any special information relating to the works

Meanwhile, if you have any questions or concerns, you can contact [email protected]

There is also a dedicated website set up for the Barrow Street Public Realm Scheme www.dublincity.ie/residential/transportation/roads-and-traffic-projects/barrow-street-public-realm-scheme

November 2024 – Week 1

Works at Phase 1B (From Grand Canal Dart Station to Ringsend Road)

  • Breaking Foothpath
  • Setting Out
  • Grouting Paving
  • Laying Clay Pipe
  • Paving
  • Erect site fencing around area works
  • Dublin city bike jigs installation

November 2024 – Week 2

Works at Phase 3A & 3B (From Mason Hayes – Ringsend Road)

  • Existing Road Gully will be removed
  • Proposed Hippo Road Gully
  • Tarmac
  • Manhole Ring Installation
  • Proposed Gully Catchpit Chamber E600 will be installed
  • Proposed Gully Catchpit manhole to be built
  • Drain Line connection
  • Setting Out
  • Breaking Footpath
  • Setting Out
  • Grouting Paving
  • Kerb Laying
  • Laying Clay Pipe
  • Paving
  • Pipe Connection into manhole
  • Set up temporary Traffic Management
  • Erect site fencing around area works
  • Phase 3A footpath work
  • Breaking footpath outside Eurospar

Actavo Contacts

All contacts

 Modular Sales Team

Modular Sales Team

Modular Sales & Enquiries

ROI Training Centre

ROI Training Centre

Dunboyne Training Centre

Network Solutions, ROI

Network Solutions, ROI

Network Solutions

In-Home Solutions, ROI

In-Home Solutions, ROI

In-Home Solutions

Ollie Raftery

Ollie Raftery

Head of Civils Division

Colin Walsh

Colin Walsh

Operations Director

Actavo Modular

Actavo Modular

Sales Team

Events, ROI

Events, ROI

Events Team

Site Accommodation, ROI

Site Accommodation, ROI

Sales Team

Actavo Civils Division

Actavo Civils Division

Events, ROI

Events, ROI

Traffic Management