Phillips 66

Term Maintenance SIP’s Contract (Scaffolding, Insulation and Painting) commenced on the Phillips 66 refinery in October 2014. A target contract for the Industrial Solutions team, they are providing access, insulation, painting, asbestos removal and fire proofing services to various areas of the refinery.

Recently Phillips 66 undertook a major turnaround, for which our team provided access, insulation, fire protection, rope access, blasting & painting works and asbestos works. Pre-shutdown works commenced in March 2015 with the shutdown being from the middle of May until the end of July. The Industrial Solutions team peaked at 225 operatives and worked a total of 125,000 man hours with no recorded accidents or incidents. All works were carried out in a safe manner, on programme and within budget. This turnaround was the largest Phillips 66 has carried out to date.